SR 80 from east of CR 833 to west of US 27
Construction Project

Project ID 408286-2-52-01

Hendry County
Expansion to four lanes

Construction began August 2012 to expand this two mile segment of existing two-lane roadway to four lanes. Crews are constructing two new 12-foot lanes to the north of existing roadway and they will become the new westbound lanes. Crews will resurface the existing two SR 80 lanes and they will become new eastbound lanes. A grassed median will separate eastbound and westbound lanes. This segment will include five-foot paved outside shoulders. The project also constructs new bridges over the Flaghole Canal, relocates utilities, and builds six stormwater retention ponds. Estimated completion is spring 2014. Project cost is $7.3 million. The contractor is C.W. Roberts Contracting, Inc.